What this guide covers
This guide helps you prepare the brief and quantities. Have the fixed 230 V supply, protection, earthing and verification designed together. For modest lighting alone, a complete extra-low-voltage garden kit may offer a different option within its manufacturer's limits.
Draw possible routes from the house. Mark paving, trees, foundations, drainage and crossings. Do not dig to a supposed universal depth found online; the installation method and site must be assessed first. Do not turn a temporary extension lead into buried or concealed permanent wiring. A fixed supply requires an appropriate design.

Copy or print your summary
This guide helps you prepare the brief and quantities. Have the fixed 230 V supply, protection, earthing and verification designed together. For modest lighting alone, a complete extra-low-voltage garden kit may offer a different option within its manufacturer's limits.
List the equipment
For each appliance, record its make, model, input power and intended position. Say which devices need to run together and whether heating or charging equipment might be added later. Include exposure to moisture, dust, cold and mechanical damage.
The load inventory adds known input powers. It preserves unknown items instead of counting them as zero. It cannot choose a circuit or cable size. Prysmian's cable guidance shows why route length and installation method matter alongside load.
Investigate before digging
Draw possible routes from the house. Mark paving, trees, foundations, drainage and crossings. Do not dig to a supposed universal depth found online; the installation method and site must be assessed first.
Mechanical excavation requires a KLIC notification. Kadaster explains the notification and utility information. Services can run through private land too. Drawings do not replace establishing the real location with the person undertaking the work.
Build a specification list
The agreed list should identify the supply cable, route protection, entries and glands, boxes, light fittings, switches, sockets, fixings and any work at the distribution board. Record who supplies each item. A Dutch grondkabel category is a starting point for finding a specified product, not a guarantee of suitability for your route.
Ask whether the exact cable is approved for the installation method. Appearance and cable family names are insufficient. Boxes and glands must form a suitable assembled system. An IP44 mark does not approve every outdoor position: Hager's IP44 range describes particular moisture and splash conditions.
For your preparation, have a tape measure, sketch, appliance manuals and access to the route. Buy cable and protective devices only after specifications are confirmed. Retail alternatives can then be compared against the same requirements.
A route-length example
A garden may be 12 metres long, while the route also includes 3 metres inside the house and 2 metres along the shed wall. That is 17 measured metres before agreed termination allowances or purchasing contingency. The calculator keeps these amounts separate. It neither selects the cable nor approves the route.
Agree who checks the installation before trenches or walls are closed and what verification and handover records you will receive. Keep a route drawing, product details and circuit description for later work.
Can an extension lead replace a permanent supply?
Do not turn a temporary extension lead into buried or concealed permanent wiring. A fixed supply requires an appropriate design.
Can I prepare the trench myself?
First agree whether this is suitable, and establish the route, utility information and working method with the contractor. Preparation must not prevent necessary inspections.
Discuss the shed supply with CAS. Include the equipment, route measurements and any preparation you hope to undertake yourself.
Materials and specifications
Before buying, check that the size, type and specification suit your installation. Use the article list and tools to work out the quantities you need.
Tape measure and plan

- Quantity and unit
- One tape measure and current plan
- Specification
- Survey accessible surfaces only; measurements do not establish electrical suitability.
Manuals and model details
- Quantity and unit
- One current manual per exact product
- Specification
- Use exact model/revision, with conflicting instructions unresolved until manufacturer/installer clarification.
Cable for a designed underground route
Specified by the electrician- Quantity and unit
- Designed route and termination allowances
- Specification
- Exact cable application, mechanical protection, route/soil/installation conditions and professional design.
- HORNBACH · Grondkabels
View range
Box and matching entries
Specified by the electrician- Quantity and unit
- From specified points/junctions
- Specification
- Box dimensions, mounting, access, entry sizes, completed-system protection and conductor space.
- Elektramat · Attema lasdoos 16 mm wit, 4 invoeren (AT2201)
View product - Elektramat · Attema kabeldoos met wartel M25 IP65 (AT2500)
View product - KARWEI · Elektradozen
View range
Sockets and switching accessories
Specified by the electrician
- Quantity and unit
- Designed functions converted to exact compatible mechanisms/frames
- Specification
- No generic approved SKU; circuit, protective conductor, mounting and exact family need assessment.
Plan route quantities
Keep each material, colour and cross-section separate. Specification is still required. A total is not a cutting plan, continuous reel length or conduit-fill calculation. Allowances and contingency are your planning choices, not installation rules.
Worked example and formula
4.2 + 2.8 + 1.5 m plus two 0.3 m allowances = 9.1 m. With a user-chosen 10% contingency: 10.01 m. A 4 m light line and 1.2 m supply route stay separate.
planned m = (sum of measured m + explicit allowances m) × (1 + contingency / 100)
Formula version 2026-10-05.1
Sources
Would you like CAS to carry out the work?
Tell us about the room, equipment and changes you need. Agree the work, checks and warranty terms before the job starts.
Discuss the workIn the event of fire or immediate danger: move to safety and call 112. Do not wait for a form reply.